Case study
Multinational Data Centre, Dublin
AEC Autodesk Awards 2022
Sisk is implementing its DPD strategy from site mobilisation right through to final handover on all of its data centre projects
Other Data Centre / ICT Case Studies
Worldport, Dublin
Worldport, Dublin
The prestigious 125,000ft² complex was a flagship development worth €38m for full service provider Worldport.
IBM Data Suite 1: IBM Technology, Dublin
IBM Data Suite 1: IBM Technology, Dublin
In January 2008, John Sisk & Son commenced the conversion of an existing production floor in Building 5, IBM Campus into a tier 3 data hall together with ancillary equipment areas valued at €10m.
IBM's data centre at Mulhuddart in Dublin is an IDA Ireland backed investment. The centre has been designed using green strategies and technology innovations to make it more energy efficient.
Although this was a standard building contract, Sisk compiled the builders work, mechanical, electrical and sprinkler bills of quantities and issued same for pricing. Fees were negotiated by the client and added to the contract cost sum. We also procured all the major plant and equipment ensuring every vendor understood and accepted the client’s terms and conditions, specification and delivery schedule.
All the interface areas between one vendor and another as well as the Mechanical & Electronic (M&E) contractors were reviewed and a responsibility matrix agreed before any orders were placed to ensure no additional costs occurred. Using our procurement tracking schedule, Sisk continually monitored the procurement of all equipment and attended any necessary factory acceptance tests.
IBM Data Suite 2: IBM Technology, Dublin
IBM Data Suite 2: IBM Technology, Dublin
Works commenced in November 2010 and completed on target in April 2011. It was constructed adjacent to the existing Data Suite 1 which Sisk constructed in 2008. The Data Suite 2 design is identical to that of Data Suite 1 with provision in place to expand the area in the future to reach the same capacity as Data Suite 1.
Data Electronics, Dublin, Ireland
Data Electronics, Dublin, Ireland
This project was constructed in two phases. Sisk was management contractor and responsible for full construction, equipment installation and hook up, coordination of client vendors, start-up, commissioning and handover of this facility to Data Electronics.
Phase 2 was completed in Feb 2011 with Phase 3 ongoing until April 2011 with a total contract value of €4.6m.
Ericsson
Ericsson
Strip out and refurbishment of existing office.
Sisk as main contractor were responsible for the design and build of the modernisation works. The works comprised alteration and modernisation to existing office and technical racking and storage space to be converted to open plan offices at Ericsson Software Campus, Athlone, Co. Westmeath.
The project was executed over a 42 week contract over five phases whilst maintaining the operations of the existing facility. A number of phases were split, creating in total seven phased operations.
The project was designed on an ongoing and phased basis to match the construction phases through a series of weekly design workshops.
Contact us and see how we can work together
Donal McCarthy
Chief Operating Officer (COO) Data Centres, Life Sciences & Technology
Donal is Chief Operating Officer (COO) Data Centres, Life Sciences & Technology. Donal has held numerous senior positions since re-joining the company in 2002 following an eight-year period working in the construction industry in New York. Prior to that he worked as a graduate engineer with Sisk, having joined the company in 1990.
Owen Sisk
Managing Director, Data Centres
Owen is one of the fifth generation of the Sisk family. In 2009 he commenced our first civil engineering project in the UK and managed much of our civils work across the UK including a number of the London 2012 Olympics projects, one of the UK’s largest onshore windfarms and other infrastructure projects.
He has led a group-wide business transformation programme over recent years and was appointed to the European business in 2019 as Regional Director, working primarily in Life Sciences. In 2022 Owen became Managing Director for Data Centres.
Vincent McCarthy
Pre-Construction Director - Data Centres, Life Science and Technology
Vincent began his career with John Sisk & Son in 1992 as a Quantity Surveyor. In 1996 he was appointed Senior Quantity Surveyor. In 2022, Vincent became Pre-Construction Director - Data Centres, Life Science and Technology.