John Sisk & Son began this project in May 1999 with a 36- week programme. The buildings are made of structural steel with the production areas clad in a Kingspan composite insulated panel and office areas clad witha Hunter Douglas architectural panel. The combined floor area is a combined 23,900m2 with marshalling yards of 6,000m2 amd 500 car parking spaces.
Over 50 subcontractors were employed on this project and upwards of 350 people during peak construction in order to meet handover dates.