Phase 1 of the hospital redevelopment included operating theatres, ICU, daycare, consultant suites, dialysis unit, surgical day wards, and concourse development.


Phase 2 commenced in August 1997, before completion of Phase 1 in October of the same year. Phase 2 delivered a new building accommodating new paediatric dept, pathology, CSSD, physical medicine.

The Hospital street constructed in Phase 1 is linked to this development by two glazed links at ground and first floors. Major refurbishment to the existing building included, a new main concourse, inner concourse, A&E dept, medical records and canteen. A new radiology dept was built within the cartilage of the existing hospital.